We will finish up the extra credit labs with a lab that helps us work with EV Analysis.

1. Estimate some PVs for each task of your project (you can be creative but for your sanity and mine, please pick numbers that are easy to work with).

2. Given your project’s task dependencies (whether or not you’ve adjusted your Gantt chart for resource balancing is up to you, but leave it uncrashed) build the time-phased baseline estimate, showing PV and cumulative PV for each time period.
3. Halfway through your project by time (or just after, if an odd # of time periods) generate a field report, coming up with data on the % complete and actual costs for each of the tasks that are appropriate to do so for. See if you can come up with a realistic but not too pessimistic scenario.
4. Calculate the cumulative EV, AC, SV and CV. Summarize in a sentence or two how things are looking for your project, and justify accordingly.
 