The figure below illustrates that task A, B, C, and D are the critical path of the project.

  • Each task is 10 days in duration and their costs are as shown in the diagram.

  • At the end of day 23, Tasks A and B are complete. Task C is 50% complete and, up to this point, $14,000 has been spent overall

1 10 11 20 21 30 31 40

A -> B -> C -> D

$5000 $5000 $10000 $15000

Notation Start Finish

Task ID

  • Planned Value (PV) = The planned value of the work planned to be done = Estimated cost of the planned work at the end of day 23 = Task A + Task B + 3 * $1,000 (Task C) = $5,000 + $5,000 + $3,000 = $13,000

  • 2. As the Project Manager (PM), at the end of Day 23, you are required to calculate the following 7 items

  • : i. AC (Actual Cost)

  • ii. BAC (Budget at Completion)

  • iii. EV (Earned Value

  • ) iv. CPI (Cost Performance Index

  • ) v. SPI (Schedule Performance Index

  • ) vi. EAC (Estimate at Completion)

  • vii. The variances (SV, CV, VAC) Part III – Square Shape.

 