solution

We have often heard that “too many cooks spoil the soup.” And indeed productivity can suffer if there is too much labor. A construction manager is trying to determine the best installation crew size for installing ceramic tile. She has tried various crew sizes with the results shown below: Crew Size (people 1 Sq Ft installed per day 2 2.890 3 3,916 4 5.012 What is the percent difference in the productivity of 3 people compared to the productivity of 2 people? Express as a percentage with no decimal places. Include a minus sign if negative. Example: Your calculator says-0.02345, you would enter -2.3 and know that means -2.3%. 1
 