Question 2: (a) A Muscat Tools company manufactures toolkits and supplies to the local and overseas market within the GCC region. In the assembly line, the kits are packed in the tool boxes. The company produces the specified demand rate of toolkit in 8 hours per day with tasks, description of tasks, and time for each task shown in Table Q2a.

(i) Draw the precedence diagram and determine the cycle time, and number of workstations;

iii) Balance the line using the longest task time rule, and determine the line efficiency.

Table Q2(a)

Demand rate (units/day)

1225

Task

Description

Time (sec)

Predecessors

A

Open tool box and place on assembly line

15

–

B

Place spanner in tool box

9

A

C

Place spark plug spanner in tool box

7

A

D

Place screw driver in tool box

7

A

E

Close internal lid

7

B, C, D

F

Place jack in tool box

18

E

G

Place jack handle in tool box

6

E

H

Place polishing cloth in tool box

7

E

I

Close tool box

10

F, G, H

J

Shrink wrap tool box

21

I

(b) A company is unable to satisfy customer demand for one of their products. The ratios for mixing the outputs from processes C, D and E are 2, 1 and 1 respectively. The ratio for the departments F and G is 3 and 1, and the ratio for departments H and I is 4 and 1. Using Table Q2(b), Determine;

(i) The system capacity and bottleneck;

(ii) How much system capacity can be gained by adding capacity to the bottleneck

Table Q2(b)

Department

Capacity (liters/hour)

Predecessors

A

350

–

B

400

A

C

350

B

D

250

–

E

200

–

F

750

C, D and E

G

300

–

H

850

F, and G

I

350

–

J

1100

H and I

K

1350

J

 