An order for 65 drain units is processed through work centers A and B. Use the following details to calculate the total manufacturing lead-time for the order and the actual percentage of time the order is running. (Provide manufacturing time answer in hours and minutes). A – Set-up time 1.5 hours A – Run time/drain 12 minutes Move time A to B 20 minutes B – Set-up time 30 minutes B – Run time/drain 2 hours Wait time between A & B 3 hours Queue time at work center A 5 hours Queue time at work center B 4 hours Move time to storage 30 minutes
 