QuestionOne–Hypothetical Case (40 Marks)

The Public Health Directorate in November 2015 anticipated the outbreak of Yellow Fever in the firstquarter of the ensuing year 2016. The Directorate subsequently asked the procurement officer to place an order for the supply of Yellow Fever vaccines.

In December, 2015,
the Procurement officer placed an order for the supply of the vaccines
but the order was silent on the strengths of the vaccine and delivery date. In January 2016,
the Head of Entity requested the Procurement Officer to brief him on
the preparedness towards the anticipated outbreak. The procurement
officer confirmed placing an order in December 2015 for the supply of the vaccines. Delivery was expected in the first quarter of 2016 before the anticipated outbreak. In February 2016,
the Procurement Officer got anxious that the vaccines had not been
delivered as expected. Sporadic cases of Yellow Fever were reported in
endemic districts in theAsemparegion of Ghana.

The
Head of Entity convened a meeting to discuss the outbreak. Public
Health practitioners in the Region confirmed their preparedness through
treatment protocols to support fieldwork in the event of an epidemic. It
became obvious that the delivery could not be made before the outbreak.
The Head of Entity accordingly requested the Procurement Officer to
brief the meeting on arrangements made for the delivery of the vaccines.

In
response, the Procurement Officer presented volumes of files in support
of orders placed. It took the meeting three sittings to retrieve a copy
of the particular contract.

When
the supplier was contacted to explain the delivery, he intimated that
he had an unlimited time for delivery as the contract was not explicit
on the delivery date. He however informed the entity that he had
pediatric doses of the vaccine which he could immediately supply.

Eventually,
there was an outbreak which claimed several lives. The Procurement
Officer insisted that he was not blamable because he had placed the order as far back as December, 2015.

Tasks:

a.Discuss the issues in the case study as related to contracting and contract management(10 marks)b.Is the Procurement Officer justified in not accepting blame? Explain your answer?(10 marks)c.What would you have done to avert the situation?(10marks)d.What recommendations would you make to avoid a recurrence?(10 marks)

 