The company uses a six month schedule, and this schedule is updated each month. The forecast
for the next six months is as follow:

JAN FEB MAR APR MAY JUN
DEMAND 5000 7000 9000 4000 5000 4000

Regular capacity is 6,000 per month. Overtime capacity is 2,000 per month. Per unit cost for labor is $1 regular time and $1.4 overtime. Inventory holding cost are $0.7 per month. The production method used is proprietary, so no subcontracting is possible.

The company plans production to minimize costs over the next six months, but plans to never lose a sale, and to maintain a minimum of 500 units in the inventory at all times to handle unexpected sales.

The current inventory level is 720.

———————————————————
Questions:
1) Produce a plan for the next six months.

2) Assume the forecast of July is 10,000 units. This unexpectedly high forecast is due to some special, one-time production. Update the six-month schedule.

3) The company has discovered a subcontractor who can handle their proprietary production method. Material costs are the same but subcontracting costs, which replace the labor costs, are expected to be $1.88 per unit. The company wishes to keep most of their production inhouse but wonders if it would be economical to subcontract some of the production for the high demand expected in July. Update the six-month schedule.

 