Suppose a project plan had three distinct paths through the network. The first path consisted of activities A (3 days), B (4 days), and C (2 days). The second path consisted of activities D (4 days), E (5 days), and F 5 days). The third path consisted of activities G (2 days), H (3 days), and I (10 days). Which is the critical path?

a. ABC b. DEF c. GHI d. ADG

 Activity slack (also known as float) can be calculated through which of the following means?

 a. Early finish (EF) – late finish (LF)

 b. Early finish (EF) – early start (ES)

 c. Late finish (LF) – late start (LS)

d. Late start (LS) – early start (ES).

 