solution

  1. JEANNA’s Welding and Upholstery Establishment needs to make 100,000 parts per month to meet demand. Each month contains 20 working days, each of which allows for 3 separate 8-hour shifts.
  1. If a worker can produce 10 parts/hour, how many workers are needed on each shift? (5 Marks)
  1. If each shift has 100 workers, what is the productivity of an individual worker? (5 Marks)
  1. If material costs are $10/part, capital costs are $100,000 and labor costs are $10/hour, what is the multifactor productivity of the plant from part (a)? (5 Marks)

b) Samantha Gayle’s newly established Agro processing plant has implemented several programs to improve its productivity. They have asked you to evaluate the firm’s productivity by comparing this year’s performance with last year’s. The following data are available:

Last Year

This Year

Output

10,500 units

12,100 units

Labor Hours

12,000

13,200

Overheads

$7,600

$8,250

Capital

$83,000

$88,000

  1. Has Gayle’s Agro processing plant improved its productivity during the past year? (7 marks)
  1. Please comments on your findings (3 marks)
 