ssxx Consider the following 2 statements, (I) and (II), as they pertain to projects and then choose the

most appropriate answer from alternatives (a) to (d)

(I) Time Constraints are typical characteristics of projects

(II) Budget Constraints are typical characteristics of projects

(a) Only statement (I) is true

(b) Only statement (II) is true

(c) Both statements (I) and (II) are true

(d) Neither statement (I) nor (II) is true

nxxThe critical path of a project network is one whose activities, when combined together, require

the least amount of time to complete (in other words, it is the shortest path in the project

network). This statement is:

(a) True

(b) False

twxxWhich of the following types of inventory does a company hold in order to protect against

uncertainty in demand, supply or lead time?

(a) Pipeline inventory

(b) Anticipation inventory

(c) Work-In-Process Inventory

(d) Cycle inventory

(e) Safety stock inventory

 