solution
Stephanie Robbins is the Three Hills Power Company
management analyst assigned to simulate
maintenance costs. In Section 14.6 we describe the
simulation of 15 generator breakdowns and the repair
times required when one repairperson is on duty
per shift. The total simulated maintenance cost of
the current system is $4,320.
Robbins would now like to examine the relative
cost-effectiveness of adding one more worker per
shift. The new repairperson would be paid $30 per
hour, the same rate as the first is paid. The cost per
breakdown hour is still $75. Robbins makes one
vital assumption as she begins—that repair times
with two workers will be exactly one-half the times
required with only one repairperson on duty per
shift. Table 14.13 can then be restated as follows:
REPAIR TIME REQUIRED (HOURS) PROBABILITY
0.5 0.28
1 0.52
1.5 0.20
| Break down number | random number | time between breakdowns | time of breakdown | time repairperson is free to begin | random number | repair time is required | time repair ends | number of hrs machine down |
|
69 |
98 | |||||||
| 2 | 94 | |||||||
| 36 | 90 | |||||||
| 49 | 36 | |||||||
| 71 | 6 | |||||||
| 99 | 78 | |||||||
| 32 | 23 | |||||||
| 10 | 67 | |||||||
| 75 | 89 | |||||||
| 21 | 85 | |||||||
| 95 | 29 | |||||||
| 90 | 21 | |||||||
| 94 | 25 | |||||||
| 38 | 73 | |||||||
| 97 | 69 |
(a) Simulate this proposed maintenance system
change over a 15-generator breakdown period.
B) Should Three Hills add a second repairperson
each shift?