A certain product has the following bill of materials. This applies to the following questions 1-5....

A certain product has the following bill of materials. This applies to the following questions 1-5. Note that the number in parentheses refers to the number of respective items needed in the assembly process.

The master production schedule for A for the next 6 weeks is shown below.

Weeks 11 12 13 14 15 16
Master production schedule 23 24 21 30 23 29

Use the above information to do your analysis in the next 5 questions.

1. What would be the gross requirements of B and C, respectively, for weeks 11-16?

Now, Assume

  • Item B’s projected on-hand at the beginning of week 11 (i.e., at the end of week 10) was 69 and we were scheduled to receive 50 on week 12,
  • The gross requirements on weeks 11-16 were as found in the information for this assignment.

Use the above information to do your analysis in the next question.

2. What would be the projected on-hand at the end of week 12? Show all your calculations.

Now assume:

  • Item C’s projected on-hand at the end of week 13 was 7
  • No scheduled receipt on week 14,
  • Gross requirements were as found in problem 1
  • The lot-sizing rule was POQ=2 weeks

Use the above information to do your analysis in the next question.

3. What should be the planned receipt on week 14? What would be the projected on-hand at the end of week 14? Show all your calculations.

Now assume: the lot-sizing rule was FOQ=200.

Use the above information to do your analysis in the next question.

4. How would the answers in problem 3 (planned receipt and projected on-hand at the end of week 14) change? Show all your calculations.

Finally, assume that the planned releases of item C were as follows:

Weeks 11 12 13 14 15 16
Master production schedule 130 210 190

Use the above information to do your analysis in the next question.

5. What would be the gross requirements of item E in weeks 11-16?

 