THree Operations Management Problems

(XTremely Fast Service Inc.) XTremely Fast Service Inc. is a call center with several business units. One of its business units, Fabulous 4, currently staffs four operators who work eight hours per day Monday through Friday. They provide customer support for a mail-order catalog company. Assume customers call Fabulous 4 during business hours and that—on average—a call arrives every 3 minutes (standard deviation of the interarrival time is equal to 3 minutes). You do NOT have to consider any seasonality in this call arrival pattern. If all four staff members are busy, the customer is rerouted to another business unit instead of being put on hold. Suppose the processing time for each call is 5 minutes on average.
What is the probability that an incoming call is not processed by Fabulous 4?
Suppose that Fabulous 4 receives $1 for each customer that it processes. What is Fabulous 4’s daily revenue?
Suppose Fabulous 4 pays $5 for every call that gets routed to another business unit. What is its daily transfer payment to the other business unit?

(Quality) Consider the following potential quality problems:
Wine that is served in a restaurant sometimes is served too warm, while at other times it is served too cold.
A surgeon in a hospital follows the hygiene procedures in place on most days, but not all days.
A passenger traveling with an airline might be seated at a seat with a defective audio system.
An underwriter in a bank might sometimes accidentally approve loans to consumers that are not creditworthy.
For each of these potential problems:
What type of data would you collect?
What type of control charts would you use?

(Teddy Bower Boots) To ensure a full line of outdoor clothing and accessories, the marketing department at Teddy Bower insists that they also sell waterproof hunting boots. Unfortunately, neither Teddy Bower nor TeddySports has expertise in manufacturing those kinds of boots. Therefore, Teddy Bower contacted several Taiwanese suppliers to request quotes. Due to competition, Teddy Bower knows that it cannot sell these boots for more than $54. However, $40 per boot was the best quote from the suppliers. In addition, Teddy Bower anticipates excess inventory will need to be sold off at a 50 percent discount at the end of the season. Given the $54 price, Teddy Bower’s demand forecast is for 400 boots, with a standard deviation of 300.
If Teddy Bower decides to include these boots in its assortment, how many boots should it order from its supplier?
Suppose Teddy Bower orders 380 boots. What would its expected profit be?
John Briggs, a buyer in the procurement department, overheard at lunch a discussion of the “boot problem.” He suggested that Teddy Bower ask for a quantity discount from the supplier. After following up on his suggestion, the supplier responded that Teddy Bower could get a 10 percent discount if they were willing to order at least 800 boots. If the objective is to maximize expected profit, how many boots should it order given this new offer?

 
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"

Managerial Decision Making Short Quiz

Question 1 (1 point)

Question 1 Saved

 

Use Excel and the data below to determine the relationship between x and y. Choose the best description of the relationship below.

x 9.5 10.0 10.0 10.0 10.3 9.1 8.6

y 370 360 400 400 420 350 310

 

Question 1 options:

  Positive Linear
  Negative Linear
  No Relationship Exists
  Do Not Know

Save

Question 2 (1 point)

Question 2 Saved

 

S&V Industries manufactures book cases. Different sizes of cases are kept in inventory. The company has 80 man-hours and 36 pounds of wood available each day. 2 pounds of wood are used to produce case x1 while 6 pounds of woods are used for case x2. Given that the optimal solution is x1 = 6 and x2 = 3.2, how much wood will be unused if the optimal number of bookcases are produced?

Question 2 options:

  none
  4.8 pounds
  8 pounds
  cannot be determined with the information given.
  Do Not Know

Save

Question 3 (1 point)

Question 3 Unsaved

 

In a production process, the diameter measures of manufactured o-ring gaskets are known to be normally distributed with a mean diameter of 80 mm and a standard deviation of 3 mm. Any o-ring measuring 75 mm or less in diameter is defective and cannot be used. Using Excel, determine the percent or proportion of defective o-rings that will be produced.

Question 3 options:

 
0.04779

 

 
0.03779

 

 
0.05779

 

 
0.06779

 

Save

Question 4 (1 point)

Question 4 Unsaved

 

Many airline flights are late for arrival. The histogram below displays the number of minutes a sample of schedules flights was late. The number above each bar is the frequency. For example, the second interval reveals that 5 flights were at least 10 minutes late but less than 20 minutes late.What percent of flights were at least 10 minutes late but less than 20 minutes late?(Enter your value in percent notation. For example, enter the value 30% as either 30 or 30%. Do not enter words, spaces, decimal point, or other marks or symbols) https://go.view.usg.edu/content/enforced/877667-WMBA6040_Quant_Spring2015_Wang_C51_CO/RspQ-Just-to-Know%20Quiz/histo1.jpg?_&d2lSessionVal=mL3JkRfFR8eWtAYUQpPACJO5I

Question 4 options:

Spell check

Save

Question 5 (1 point)

Question 5 Unsaved

 

Given the following linear programming model: minimize C = 5×1 + 4×2 subject to 6×1 + 10×2 equation300 10×1 + 4×2 equation200 x1, x2 equation0 Its solution is:

Question 5 options:

  x1 = 1, x2 = 30
  x1 = 56, x2 = 0
  x1 = 10.53, x2 = 23.68
  x1 = 20, x2 = 0
  Do Not Know

Save

Question 6 (1 point)

Question 6 Unsaved

 

Karim’s Oak Furniture Company manufactures oak tables and chairs. To manufacture the chairs and tables, the wood must be cut, glued, and finished. The labor requirements for the three steps are in the table below, as well as the profit for each table and chair. The available time for the labor requirements are 40 hours for cutting, 40 hours for gluing, and 40 hours for finishing.Karim wants to determine the number of tables and chairs to manufacture in order to maximize profit.What are the decision variables? https://go.view.usg.edu/content/enforced/877667-WMBA6040_Quant_Spring2015_Wang_C51_CO/RspQ-Just-to-Know%20Quiz/karim_table_p_1_a.jpg?_&d2lSessionVal=mL3JkRfFR8eWtAYUQpPACJO5I

Question 6 options:

  x1 = the number of hours to make a table,x2 = the number of hours to make a chair
  x1 = the number of hours required to cut, x2 = the number of hours required to glue, X3 = the number of hours required to finish
  x1 = the number of tables, x2 = the number of chairs
  x1 = the profit per table, x2 = the profit per chair
  Do Not Know

Save

Question 7 (1 point)

Question 7 Unsaved

 

For the data set below, use Excel to determine the slope, the rate of change of y for a one-unit change in x. https://go.view.usg.edu/content/enforced/877667-WMBA6040_Quant_Spring2015_Wang_C51_CO/RspQ-Just-to-Know%20Quiz/regr_data_table.gif?_&d2lSessionVal=mL3JkRfFR8eWtAYUQpPACJO5I

Question 7 options:

Spell check
 
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"

Project Management Ch 4

1.The method used to collect information to use through all phases of the project life cycle is called
A) Responsibility matrix
B) Organization breakdown structure
C) Work breakdown structure
D) Priority matrix
E) Work package

2
The first step in creating the necessary information to manage a project is to
A) Establish project priorities
B) Define the project scope
C) Verify the budget available
D) Assign team members to work on the project
E) Determine the required completion date

3
Research shows the most frequently mentioned barrier to project success is
A) Not enough budget resources
B) Poor performance by team members
C) Weak project leadership
D) Poorly defined scope or mission
E) Political in-fighting

4
An expected output over the life of a project would be classified as
A) A deliverable
B) A product
C) An end object
D) An objective
E) A target

5
The ability of 911 emergency systems to identify the caller’s phone number and location are considered to be a
A) Technical requirement
B) Milestone
C) Project limit
D) Project exclusion
E) Project deliverable

6
“To construct a high-quality, custom home within five months at costs not to exceed $150,000” is best classified as
A) A deliverable
B) A milestone
C) An objective
D) A limit
E) An exclusion

7
Which of the following is not one of the basic classifications of project priorities?
A) Profit
B) Cost
C) Time
D) Performance
E) All of these are basic classifications

8
If a project criterion indicates that the project must meet a specific date, that criterion is classified as
A) Constrained
B) Enhanced
C) Accepted
D) Limited
E) Fixed

9
The tool used to assist in making project trade-offs between schedule, budget, and performance objectives is called a
A) Responsibility matrix
B) Work breakdown structure
C) Project priority matrix
D) Work package
E) Criterion matrix

10
The highest element in the hierarchical breakdown of the WBS is
A) A work package
B) Sub deliverables
C) A cost account
D) Major deliverables
E) The project

11
All of the following are usually included in a work package except
A) What will be done?
B) The time needed to complete the work
C) A single person who is responsible for its completion
D) All the costs for the work package
E) All of these are included in a work package

12
The final step in the creation of a Work Breakdown Structure is to
A) Code the WBS for tracking
B) Assign the cost account to a manager
C) Assign the work package to a manager
D) Develop the responsibility matrix
E) All of these are included in the final step

13
The intersection of the WBS and the OBS is called the
A) Responsibility matrix
B) Priority matrix
C) Work package
D) Cost account
E) Project overlap

14
If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice?
A) Responsibility matrix
B) Organization breakdown structure
C) Work breakdown structure
D) Priority matrix
E) Process breakdown structure

15
The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called:
A) Scope erosion
B) Scope creep
C) Project bloat
D) Scope enhancement
E) Project add-ons

 
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"

Purposeful Sampling and Saturation

Purposeful Sampling and Saturation

Qualitative research is fundamentally framed by a research problem which is the need for the research, a research purpose which reflects the intent, idea, or objective underlying a study, and the research questions which constitute questions that the data gathering will help to answer (Creswell, 2009). In qualitative research, data gathering or sampling strategy to answering research questions is by two means or sources-site and participant (Maxwell as cited in Ravitch & Carl, 2016) since in essence, the research problem initiates the study whiles the study purpose and study questions inform the sampling strategy (Creswell, 2009). The ensuing discussion is designed towards critiquing the sampling strategy employed by Yob & Brewer (n.d.) vis-a-vis the article under review.

Research Purpose, Research Questions, and Research Site

An exemplary research purpose entails ideas about the research participant and sites and details about the central phenomenon being explored (Creswell, 2009). A qualitative research purpose also reflects an evolving or developing design and the use of words from a qualitative research vocabulary (Schwandt as cited inCreswell, 2009). Developing their research from the problem of lack of references for understanding missionary activities regarding “online and geographically dispersed programs” (Yob and Brewer, p. 3) Yob and Brewer’s (n.d.) intention was to innovate references of understanding aimed at helping towards the facilitation of curriculum and student study and service initiatives development regarding positive social change. Yob and Brewer’s (n.d.) research purpose vis-à-vis purpose statement invariably entailed ideas of research participants namely members of the university (faculty, students, and alumni), of a distance learning university involved in positive social change initiatives (site), and details of the central phenomenon, which is understood as an institution of higher education’s “mission of creating positive social change…. defined as the reaching out to their neighborhoods as a member of the community to contribute to the common good through research, service, and educational opportunities” (Yob & Brewer, n.d., p. 2).

Although research questions are central to qualitative research in that they are used to guide the research (Ravitch & Carl, 2016) the authors notably, did not explicitly state their research questions. Thus, a reader needs to deduce from the interview questionnaires, codes, and themes or answers to get the import of how the author understood or explained the problem.

Researchers Purposeful Sampling Strategy

A purposeful sampling strategy constitutes the selection of: respondents for a study based on their identity as having study related knowledge of study phenomenon and resides within the site of the study; site; and so forth (Ravitch & Carl, 2016). Yob and Brewer (n.d.) sort to help universities innovate curriculum in the direction of developing student’s effort towards positive social change by providing references of understanding regarding positive social change based on prevailing meanings and practices surrounding positive social change activities. In order to create meanings of positive social change mission or efforts to provide the references of understanding and hence themes of positive social change to augment the lack thereof in scholarship and practice, Yob and Brewer (n.d.) adopted a purposeful sampling strategy that fundamentally the involved the selection of thirty individuals of the university with backgrounds in positive social change activities or identified to have participant experiences in positive social change activities. Yob and Brewer (n.d.) also adopted a site-a distance learning institution that characterizes among many the primacy of online and a geographic dispersing of the individual. Details of Yob and Brewer’s (n.d.) study, however, were not illuminating enough to warrant a clear definition of the purposeful sampling strategy. Notwithstanding, with the understanding that “multiple strategies can be used to achieve purposeful sampling strategy” (Ravitch & Carl, 2016, p. 128) the above details indicate that the authors’ purposeful sampling strategy best reflects the combined characteristics of the “instrumental-use multiple-case sampling” (Ravitch & Carl, 2016, p. 134) and “key informants, key knowledgeable, and reputationalsampling” (Ravitch & Carl, 2016, p. 134) where cases are chosen towards the development of generalizable finding to facilitate the enactment policy, program, and practice changes and individuals are selected based on knowledge, reputational influence to provide insight and clarity regarding the issues being inquired about (Ravitch & Carl, 2016) respectively.

Alternative Data Collection Strategy

Data collection in qualitative research is a process characterized by relatedness and iterations involving the generation and coconstruction of data (Ravitch & Carl, 2016). Thus qualitative data collection strategy should be dynamic in combining elements of interviews, surveys, focus groups, observation fieldnotes, archival and participants generated documents and media, and researcher memos and journals (Ravitch & Carl, 2016). Aside from generating data from mainly, interviews via telephones vis-Ă -vis transcriptions and observations, Yob and Brewer (n.d.) could have enhanced the dynamic or multidimensional nature of the process by infusingcoconstructive and generational methods that involves focus group interview, reflexivity, memos, contact summary forms, research logs towards achieving complexity and richness. The lack of these generative and coconstructive in the authors’ data generation strategy explains the limit in richness and complexity of the study.

Evaluation of Researchers’ Data Saturation Approach

Data saturation can be defined as “the point at which no new information or themes are observed in the data” (Guest, Bunce, & Johnson, 2006, p. 59). Operationally, data saturation occurs when emerging information introduced into the data collection and analysis process generate little or insignificant alterations to the codebook (Guest, Bunce, & Johnson, 2006) thus, when significant thematic developments and coding is exhausted (Guest, Bunce, & Johnson, 2006). To Morse (as cited in Guest, Bunce, & Johnson, 2006) “at the crux of the discussion is how and when we define themes and how we eventually plan to present our data” (p. 77) which is solely at the discretion of the researcher vis-à-vis related factors such as resourcefulness as well as the relationship between the themes, data, and codes: in that codes are applied to data which in turn generate themes (Guest, Bunce, & Johnson, 2006). Yob and Brewer (n.d.) intended to generate themes that give practical meaning to the concept of positive social change mission in higher education settings. Although they did not explicitly indulge the reader in their concept and practice of saturation, by implication, vis-à-vis the research questionnaire and iteration frequency regarding interviews and coding one can argue that the authors’ data, codes, and theme, were related and aligned with the research questions and ultimately the research purpose.

Conclusion

It is evident that the qualitative strategy of inquiry is emergent or evolving. Evidently, the requirement for categorization of purposeful sampling strategy and data saturation are inexhaustive and emergent(Patton, 2015). Per the study of Yob and Brewer (n.d.) one can tell that a sampling strategy may reflect elements of more than the defined purposeful sampling strategy current identified by Patton (2015) while ultimately, a good qualitative research sampling strategy must reflect the participant and site of the study (Ravitch & Carl, 2016) associated with good research purpose (Creswell, 2009) data generation, coding, and thematic development (Guest, Bunce, & Johnson, 2006).

References

Creswell, J. (2009). Research design: Qualitative, quantitative, and mixed methods approaches (Laureate Education, Inc., custom ed.).

 

Thousand Oaks, CA: Sage Publications.

 

Guest, G., Bunce, A., & Johnson, L. (2006). How many interviews are enough? An experiment with data saturation and variability. Field

 

          Methods, 18(1), 59–82.

 

Patton, M. Q. (2015). Chapter 5, Module 30: Purposeful sampling and case selection: Overview of strategies and options. In Qualitative

 

research and evaluation methods (4th ed., pp. 264–315). Thousand Oaks, CA: Sage Publications.

 

Ravitch, S. M., & Carl, N. M. (2016). Qualitative research: Bridging the conceptual, theoretical, and methodological. Thousand Oaks,

 

CA: Sage Publications.

 

Yob, I., & Brewer, P. (n.d.). Working toward the common good: An online university’s perspectives on social change, 1-25.

 