solution
A company builds custom equipment. It has landed a contract with a major customer Relevant data are shown below. The complication is that the delivery has been promised in 32 weeks and the company will have to pay a penalty of $375 for each week the equipment is late Develop the minimum cost crashing schedule. Crashing cost Imediate Predecessor() Activity Normal Time week) 9 Ist Week 2nd week 410 5 415 125 K ? N X 5 45 300 45 350 M J N 50 200 225 Q J, M 5 P Y 9 90 85 90 End Y, The critical path after crashing is (Click to select) Expected duration of the project after crashing is weeks.