Development of Version 2.0 of a particular accounting software product is being considered by Jose? Noguera’s technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following? table:

Activity

Normal Time? (weeks)

Crash Time? (weeks)

Normal Cost

Total Cost with Crashing

Immediate? Predecessor(s)

A

4

3

$2,200

$2,800

—

B

2

1

$2,200

$2,800

—

C

3

3

$500

$500

—

D

8

4

$2,500

$2,820

A

E

6

3

$900

$1,350

B

F

3

2

$3,200

$4,600

C

G

4

2

$1,500

$2,000

?D, E

?a) Based on the given information regarding the activities for the? project, the project length? = ____weeks.

b) The total cost required for completing this project on normal time = $___________

c) For reducing the duration of the project by one week, the activity that should be crashed first is activity _________. The cost of the project based on the first activity selected for crashing will increase by $_________.

d) The maximum weeks by which the project can be reduced by crashing = _________weeks

 