You are the project manager of the Community Hall Project. You received the following data from your project controls manager. The project was planned for to take 10 months and the detail provided is in line with the current execution schedule.

Values per month for the community Hill Project
Month Actual cost of work performed Budget cost at completion % planned % physically completed
1 1328 1328 3.0 1
2 1256 1156 6.0 8
3 4728 4018 10.0 9
4 2065 1755 11.0 6
5 31207 28 526 4.0 18
6 40 517 40 101 11.0 6
7 16 783 26 872 22.0 15
8 20 470 28 507 8.0 1
9 25 600 23 933 10.0
10 41 568 21 640 15.0 8

3.1. Provide feedback on the project to the project sponsor in the form of a line graph. indicating the actual cost (blue), budgeted cost at completion (red) and earned value (green). The graph must also show legends and titles. (10)

3.2. The project sponsor must provide feedback on the following:

3.2.1. In which month/s was the project ahead of schedule? Provide proof with SPI values. (3)

3.2.2. In which month/s was the project ahead of cashflow? Provide proof with CPI values. (3)

3.2.3. Was the project managed successfully to the end? Provide proof. (4)

3.2.4. In which months was the earned value not at its optimal level? Provide proof. (3)

 