Assume the source selection criteria for evaluating proposals for a project is as follows:

Management approach 15%

Technical approach 15%

Past performance 20%

Price 20%

Interview results and samples 30%

Use Figure 5-24 as a guide and the supplier evaluation template from the companion Web site to calculate the total weighted scores for three proposals. Enter scores for Proposal 1 as 80, 90, 70, 90, and 80, respectively. Enter scores for Proposal 2 as 90, 50, 95, 80, and 95. Enter scores for Proposal 3 as 60, 90, 90, 80, and 65. Add a paragraph summarizing the results and your recommendation on the spreadsheet. Print your results on one page.

 