The table below shows the relevant task data for a future design project. Draw in Word or other software of your choice, a fully analyzed network diagram for this project, showing all activity times. Scans of manual drawings pasted into Word are not acceptable for grading. Develop an Activities Boundary Timetable identify the critical path and determine the project duration. Don’t use MSP for this problem! Save your Word file under the name Test2Q2. Task Immediate Duration Predecessors (weeks) A 3 B 5 ? D B 4 AB 6 7 DE 4 H F, E 5 B 3 MOA LOT E F G AB
 