Altex Corporation Case Study
Read Case 3: Altex Corporation in the case study section of your text. Write a summary of the case and answer the following questions from the end of the case.
- Why was a risk management plan considered unnecessary?
- Should risk management planning be performed in the proposal stage or after contract award, assuming that it must be done?
- Does the customer have the right to expect the contractor to perform risk analysis and develop a risk management plan if it is not called out as part of the contractual statement of work?
- Would Altex have been more interested in developing a risk management plan if the project were funded entirely from within?
- How might the Army have responded if they were presented with a risk management plan early during the R&D activities?
- Can risk management planning be justified on almost all programs and projects?
Your paper must be 2-4 pages in length (not including title and reference pages), doubled spaced, and formatted according to APA style as outlined in the approved style guide. A minimum of two sources, including the text, must be used to complete this assignment
Link for course material
Running head: RISK MANAGEMENT 1
Risk management Process: Altex Corporation
Brandon Ellison
BUS 697
Dr. Shawn Milligan
– 1 –
1
2
1. where is your introduction?
[Shawn Milligan]
2. All assignments in this
class are academic papers
and should include
introduction, conclusions,
thesis statements, and
conceptual headers.
Academic papers allow you to
demonstrate that you can
write clearly and think
critically. Question and
Answer do not show these
skills. [Shawn Milligan]
RISK MANAGEMENT PROCESS 2
Why a risk management plan was considered unnecessary?
Risk management process can be considered unnecessary at times (Viscione, 2012).
Though, this is a bit risky as the process is very important in any project. The need for the risk
management process is to prevent the future risks that could affect this project. The risk
management process involves the identification, analyzing, the planning and the control of the
potential risks. The risk was considered unnecessary due to various reasons. One, it would be an
added cost to the organization that was not accounted for and two; it was not on the part of the
contractual statement of work.
Should risk management planning be performed in the proposal stage or after contract
award, assuming that it must be done?
Management plan is very important to the organization. It should be done on time so as to
ensure that the organization is well managed effectively. Risk management is central to the
issues o planning in the long run. We have reasons as to why this timing should be properly
timed. One, risk management is pro active. They should hence be performed in the proposal
rather than after the contract award. This is because they are more useful while performed at the
proposal stage rather and less useful while performed after the contract award (McMullen, 2013).
Managers should hence initiate risk management planning at the proposal stage for them to be
more useful to the organization.
Does the customer have the right to expect the contractor to perform risk analysis and
develop a risk management plan if it is not called out as part of the contractual statement
of work?
– 2 –
1
2
3
4 5 6
78 9
10
11
1. Do the companies need to
ask for a risk management
proposal? I believe risk
management should be taken
into account when putting
together the bid. If you the
bidder does not know the
risks, how can they
adequately plan for how these
risks will affect their budget,
timeline, and scope? For
example, if you are building a
bridge, you will want to make
sure to include money for
traffic control personnel and
extra time and money for
weather related issues, this is
done at part of the risk
management plan. [Shawn
Milligan]
2. There are issues with your
paper that you should have
caught if you had read your
paper out loud or used
Natural Reader.
Natural Reader:
http://www.naturalreaders.co
m/ Natural Reader is a free
text-to-speech software.
Students are always amazed
(and often a bit horrified) at
the number of writing errors
they hear when the Natural
Reader reads their paper. Try
it, it really does work.
[Shawn Milligan]
3. on time
what is on time? When should
it be done? [Shawn Milligan]
4. o
wrong word [Shawn Milligan]
5. We
First person is allowed in APA
only when it is absolutely
necessary and it is not
absolutely necessary here.
This sentence could have
been written in the third
person. Understanding when
and how to use first person is
sometimes tricky. Here are
some sources for more
information: •
https://owl.english.purdue.edu
/owl/resource/560/15/ •
http://www.louis-hoffman-
virtualclassroom.com/psychol
ogy%20resources/writing%20
resources/first_person_apa_s
tyle.html •
http://www.typepad.com/servi
ces/trackback/6a01157041f4e
3970b0120a5b49ccc970c
[Shawn Milligan]
6. have reasons as to why this timing should be properly
this sentence does not say anything…. [Shawn Milligan]
7. They
Company Pronouns When referring to an entity (like a company, government
agency, or a country), use the pronouns “that” or “it.” Entities are not people,
so it is incorrect to use “who” or “they” or “their” when referring to them. If
using “it” and “that” sounds awkward rewrite the sentence and use the
entities name instead. For additional information see:
http://www.quickanddirtytips.com/education/grammar/is-it-%E2%80%9Ca-
company-who%E2%80%9D-or-%E2%80%9Ca-company-
that%E2%80%9D#sthash.5cX7HRH1.dpuf [Shawn Milligan]
8. timed.
Vary your word choice to avoid redundant words and phrases. [Shawn
Milligan]
9. active. They should
– 2 (cont) –
What is they? Vague pronoun reference. If you made sure the
reader knows what your pronouns (he, she, they, us, it) refer
to, your writing will be much clearer. For additional information
see: http://www.dummies.com/how-to/content/how-to-avoid-
vague-pronoun-references and
http://bcs.bedfordstmartins.com/everyday_writer/20errors/2.ht
ml [Shawn Milligan]
10. they
unclear [Shawn Milligan]
11. hence
try to avoid. you are overusing this word [Shawn Milligan]
RISK MANAGEMENT PROCESS 3
The customer has no right to expect the contractor to perform a risk management and
develop a risk management plan if it is not called out as part of the contractual statement of
work. It is always advisable to follow the opinions of one’s customers so as to make them happy
with the services that they are given. No one has them has the authority over the other, both the
employee and the customers (Viscione, 2012). Strategies of the project are defined early so as to
come up with the requirements of the job. It is also available for laying down the job breakdown
structure. This is hence the reason why the customer cannot demand for the contractor to perform
any kind of work as a risk analysis or management plan if it was not part of the contractual
statement.
Would Altex have been more interested in developing a risk management plan if the
project were funded entirely from within?
Yes, Altex should have been more interested top perform the risk management plan even
though the project would have been funded entirely from within. First of all, it is important to
note that the risk management process is very vital to an organization. It involves all the
strategies that are required in ensuring that there is risk identification, risk analysis and risk
mitigation. So, even if the process was funded from within, there is still the need to have a risk
management plan (McMullen, 2013).
How might the Army have responded if they were presented with a risk management plan
early during the R&D activities?
It might be difficult for the army’s if they were presented with a risk management plan
during the early stages of the R & D activities (Viscione, 2012). This is because; the whole
– 3 –
1
2
3 4
5
6 7 8
9
1. The customer has no
right to expect the
contractor to perform a risk
management and
develop a risk management
plan if it is not called out as
part of the contractual
statement of
work.
do not agree…. [Shawn
Milligan]
2. Do you feel ethics come
into this issue?…I certainly
do…. [Shawn Milligan]
3. It is always advisable to
follow the opinions of one’s
customers so as to make
them happy with the
services that they are
given.
ethical issue here – do not
agree in this instance.
[Shawn Milligan]
4. No one has them
This sentence is hard to
follow. How might you reword
it to make your point clear to
the reader? [Shawn Milligan]
5. Strategies of the project
are defined early so as to
come up with the
requirements of the job. It
is also available for laying
down the job breakdown
structure. This is hence the
reason why the customer
cannot demand for the
contractor to perform any
kind of work as a risk
analysis or management
plan if it was not part of the
contractual
statement.
unclear… And the customer
does have the right to expect
the contractor to do the job
they were hired to do. Lots of
ethic issues here you missed.
Needed more analysis.
[Shawn Milligan]
6. This is a possessive
apostrophe error. [Shawn
Milligan]
7. army’s
Capitalization error. [Shawn
Milligan]
8. they
it Company Pronouns When referring to an entity (like a company,
government agency, or a country), use the pronouns “that” or “it.” Entities are
not people, so it is incorrect to use “who” or “they” or “their” when referring to
them. If using “it” and “that” sounds awkward rewrite the sentence and use
the entities name instead. For additional information see:
http://www.quickanddirtytips.com/education/grammar/is-it-%E2%80%9Ca-
company-who%E2%80%9D-or-%E2%80%9Ca-company-
that%E2%80%9D#sthash.5cX7HRH1.dpuf [Shawn Milligan]
9. R & D activities
write out In American Psychological Association (APA) abbreviations should
only be used when the abbreviation is well known and will not interfere with
the reader’s understanding or when the term is used repeatedly in the paper.
The first time an abbreviation is used it needs to be identified with the
abbreviation. For example Project Management Maturity Model (PMMM). For
additional information on abbreviations see:
https://owl.english.purdue.edu/owl/resource/560/21/ [Shawn Milligan]
– 3 (cont) –
RISK MANAGEMENT PROCESS 4
process is also complex in the long run. The risks might be so many and hence the army would
be confused. In the long run, why should they be exposed to situations like this and open a
Pandora’s Box for them?
Can risk management planning be justified on almost all programs and projects?
Yes, risk management planning can be justified necessary on most all projects. This is because
they are very necessary to the organization. It is through the risk management processes that the
managers are able to be protected so as to identify, plan, analyze and control all the risks that
could affect a project. It reduces the costs that could be incurred in the organization if the risk
management was not initiated (Viscione, 2012). It also raises the expectations of the organization
and managers since there are assured of lesser risks affecting the project (McMullen, 2013).
There is hence the importance of considering the risk management processes in almost all
projects.
– 4 –
1
2
3
1. Yes,
APA does not use block style
paragraphs. The first
sentence for each paragraph
needs to be indented.
[Shawn Milligan]
2. they are very
it is unecessary [Shawn
Milligan]
3. Where is your conclusion?
All academic papers (actually,
discussion posts, speeches,
letters…) need to have both
an introduction and a
conclusion. Your conclusion
should serve to reestablish
your position on this topic and
your thesis and often mirrors
your introduction. Your
conclusion should not include
any new information. For
more information on how to
develop a proper conclusion
see:
https://owl.english.purdue.edu
/owl/resource/724/04/
[Shawn Milligan]
RISK MANAGEMENT PROCESS 5
References
McMullen, T. B. (2013). Introduction to the theory of risk management system. Boca Raton
[Florida: St. Lucie Press.
Viscione, J. A. (2012). How to construct an efficient program and project. New York, N.Y:
National Association of Credit Management.
– 5 –
[no notes on this page]
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"
